With more complex and substantial machining demands for projects, Ekspan now operate a state-of-the-art Hurco DCX3226i CNC machine, an essential addition to their in-house manufacturing facilities.
USL Ekspan is the UK's largest quality bearing supplier and installer to meet demands both in the UK and worldwide.
USL Ekspan install an extensive range of mechanical and elastomeric expansion joints and seal joints to CD358 standards.
Bridge jacking and temporary works are an essential part of most bearing replacement and refurbishment operations, ensuring works are carried out safely and efficiently without affecting the integrity of the structure.
The importance of carrying out bearing and expansion joint inspections by proficient and competent engineers who understand their functionality can often be key to maximising a structure’s lifespan and avoiding major, unexpected, emergency repair costs.
USL Ekspan have carried out a number of projects for swing bridges and foot bridges. From design, fabrication of all structural components, to trial erection and final installation. Details of these type of bridge installations can be supplied on request.
Background
Queensgate Footbridge, which crosses over the A15 Bourges Boulevard near Queensgate Shopping Centre, provides a popular link to the city centre from Peterborough’s railway station. With nearly 40 years of public use and constant wear the structure was in need of essential refurbishment and repair.
As part of the £9.5 million investment for the regeneration and economic development of Peterborough’s City, Skanska in working partnership with Peterborough City Council, commissioned Ekspan to deliver the refurbishment of Queensgate Footbridge.
USL Ekspan’s Workscope
Working to the client’s drawings and specification, USL Ekspan’s programme of works included removal of the existing roof soffit panels; removal of roof cladding and flashing; removal of window glass and aluminium frames. In addition temporary edge protection was installed after removal of the windows.
Offsite - Lifting of assembled roof onto crane for transportation to site for final installation by USL Ekspan
Night Works - Welding and installation of aluminium frames
Site works included a combination of both day and night working hours to suit the construction programme and accommodate lane closures for both removal and installation phases. All deadlines were met accordingly with least disruption caused to the public.
New components and steel works were fabricated and installed, including the roof frame, cladding and flashing, and a permanent stainless steel handrail. The deck and various service ducts were then reinstated, as well as steelwork repairs on the access ramps.
Supply and assembly of the zinc roof cladding was carried out by a roof specialist sub-contractor and then transported to site for installation by USL Ekspan. Supply and final installation of the glass panels was arranged by the main contractor.
Queensgate Footbridge Completed - Interior view
The refurbished footbridge with the coloured glass panels has been well received providing a more modern fresh look.
For more information please contact +44 (0) 113 8418861 or email info@uslekspan.com
Download PDF